Each tower was calculated to weigh 300,000 metric tonnes which would be spread over a large concrete slab called a mat. But that weight exerted 1,140 kilopascals (one kilopascal pressure is equivalent to 1kg exerting pressure on 1sq mm), exceeding the weight-bearing capacity of the soil and enough to cause the foundation to fail.
Moreover, soil tests showed that the bedrock under both towers started shallow, 15m down, but sloped sharply to more than 180m.
To support the immense weight, a depth of 21m (as high as a five-storey!) would have to be excavated for the basement. This also meant penetrating the bedrock at one end but not the other.
Installing concrete-filled piers at the deep end would be difficult, slow and expensive, exceeding normal construction practices. The piers' shortening over time would also produce unacceptable tower tilting. (See diagram a)
KLCCB (Kuala Lumpur City Centre Bhd), the developer of KLCC, finally decided to move the location 60m southeast of the initial site to achieve better support. Here, the bedrock was deeper, thus allowing the buildings to be firmly anchored in at least 55m of soil for each tower basement.
And instead of piers, it was decided an entirely different foundation system was needed. Friction piles (structures narrower than piers), reinforced by grout (a sand and cement mixture), were used.
Excavation began in March 1993.
The contract for the foundation works was awarded to a consortium of French and local companies, Dragages-Bachy-First Nationwide Sdn Bhd.
To dig the foundation, we didn't use hammering in the conventional sense. Instead we excavated the ground using a combined technique of piling and raft foundation (like a big concrete slab); it was the first time the latter technique was being used in the country.
With this technique, when you bore the piles in, instead of circular piles, rectangular or barrette ones were used. Barrette piles are bigger than circular piles, so we could put in fewer number of piles. This also increases the safety margin and poses fewer problems.
That's because the bigger the pile is, the smaller the number we have to put in and the better its ability to withstand tension.
Water was then used to clean and keep the bored hole intact until we poured the concrete in. Until a certain depth, drilling mud or bentonite (a kind of "clayish" liquid)
was used instead of water as it was a stronger substance which could do the job more effectively in deeper parts," explains Arlida who's now the general manager of KLCCB and project management consultant for Putrajaya Holdings Sdn Bhd.
It was also the first time that the Malaysian construction industry would witness the largest amount of concrete poured in its history - 13,200cu m (enough to build 130 double-storey link houses!).
The concrete was continuously poured into the hole for more than 52 hours in order to eliminate construction joints in the pile mat and achieve a smooth finish.
According to KLCCB general manager Hashimah Hashim, then the project manager of Tower One, the construction industry normally uses grade 30 or 40 concrete. For the towers, high-strength grade 80 concrete was used.
The use of such high grade concrete was a transfer of technology from the USA which uses up to grade 110 in the construction industry," he says.